Australia’s 2030 Smart Meter Rollout: Are We Going Hit Targets – Really?

Learnings from the UK Smart Meter Rollout Experience.

Since smart meters (SM) were mandated for the National Energy Market in 2018, just 30 percent of the rollout is complete.

Six years into the program, in April last year, the AEMC found “industry widely agreed that the current approach to legacy meter replacement will not lead to smart meters being deployed fast enough to support the transition to the future energy system.”

Unless completed by 2030, the energy regulator admits Australia’s smart meter implementation will disadvantage consumers. In fact, the cost of missed benefits to consumers can’t be offset by the savings attributed to a slower approach. The project was already set to cost $2.48Billion. The AEMC’s recent rule changes designed to accelerate rollout plans adds approximately $120.8 million to this total.

Oof, so, the stakes are high; by its own admission, if the AEMC can’t coordinate a successful smart meter rollout in the next five years, it has either wasted more than $120million, cost customers the equivalent in lost benefits, or both.  In the meantime, Australia’s capability to reduce carbon emissions, increase the adoption of renewables, and ensure equitable access to affordable energy is also severely impacted.

What Are Accelerated Smart Meter Implementation Targets and Factors Impacting Rollout Rates?

AEMC’s 2022 proposal to shift from 30-100% digitisation of the NEM with smart meters by 2030 is ambitious. While reforms are underway to enable targets, it’s worth noting recent UK Government reports regarding Great Britain’s smart meter rollout which bears a strong resemblance to our own.

AEMC’s costs and target dates are based on several important assumptions. So, we’re here to ask: how likely it is that Australia will successfully implement smart meters across the NEM by 2030 in light of learnings from the UK experience, including:

  1. Past Performance
  2. Feedback from Suppliers (Smart Meter Installers)
  3. Failings in the Regulatory Approach
  4. Installation Hurdles
  5. Skills Shortages
  6. Technical Issues

1. Past Performance

The AEMC’s national smart meter rollout bears startling resemblance to that in the UK.  For example, just 57% of homes and businesses across the UK have been digitised since smart meter mandates in 2008. 

The UK Government’s original target for a completed smart meter rollout was 2019. Since, deadlines have been adjusted three times and target penetration for smart meters reduced from all homes and small businesses in 2019, to its current target of 74.5 percent of homes and nearly 69 percent of small businesses by the end of 2025.

A decade into the rollout, at the end of March last year, only 57 percent of all UK electricity and gas meters were smart.

2. What’s Slowing Smart Meter Implementations? The Feedback From UK Suppliers

The UK’s energy regulator, Ofgem assigned responsibility for Great Britain’s smart meter rollout to energy suppliers in 2008. Suppliers are bound to targets set each financial year. Yet just 3.7 million or a targeted five million meters were implemented in 2022; only one of thirteen suppliers reached their rollout target.

Suppliers complain that original and accelerated target dates are too difficult to achieve. They cite reduced demand, skills shortages and market variances, amongst other impediments to reaching goals.

For instance, the Smart Energy GB Outlook Tracker study in November 2022 found implementations in households that actively want a smart meter to be completed, making it increasingly challenging to encourage take-up with remaining properties. 41 percent of UK households without a smart meter has concerns about the tech. Meanwhile, the very nature of business means suppliers serve different regions and target markets, making a fair comparison of their rollout performance, and associated penalties, impossible.

3. How the “Regulatory Approach” Has Impacted Smart Meter Rollouts

Indeed, feedback from UK suppliers highlights how opting for the traditional regulatory approach, rather than a customer-motivated transition to smart meters has contributed to several issues.

For instance, targets prioritise quantity over the quality of installations. Today, more than one million UK smart meters aren’t working because they weren’t installed properly. With incentives based on new device installations, faulty smart meters aren’t being fixed or reinstalled by suppliers.

Rather than punishing suppliers for not hitting installation figures, experts recommend customer sentiment and consumer behaviour becomes a focus to enable targets. Indeed, energy consumers are often overlooked in Australia’s own rollout.

Tens of thousands of UK customers are rejecting smart meters, either because of bad experiences with either suppliers applying pressure to install a smart meter (to hit targets), or fear of being swapped over to ‘smart prepayments. Similar issues feature in Australia, with customers experiencing bill shock having been placed on a time-of-use tariff at the point of a smart meter installation with no notice.

Unless consumers feel safe with smart meters and see the benefits, suppliers and energy regulators are only going to find it more difficult to hit installation targets – especially with willing smart meter consumers shrinking in number. UK energy suppliers haven’t been able to convince individuals to convert to smart meters. With assistance from Energy Consumers Australia (ECA), the AEMC has started to review its own community engagement programs a way to reduce consumer resistance and trigger more requests for smart meters necessary for the accelerated rollout.

Meanwhile, Australian energy retailers are rightfully concerned about the burden of longer notice periods and providing more customer data on smart meters and impacts upon pricing. Unless tariff options are more attractive, more information may, in fact diminish any enthusiasm for smart meters. Indeed, the ACCC has recommended consumers maintain the option of a flat-rate tariff once a smart meter is installed.

4. Installation Hurdles Slowing Smart Meter Rollouts

In addition to “difficult” customers, UK energy suppliers are struggling to implement smart meters in a range of settings. This includes rentals, inner-city apartments, and rural or remote customers with no mobile coverage.

Penetration of smart meters in London is significantly lower than the national average (43 percent vs 57 percent) due to parking, higher costs, and high rates of apartment living. Devices in apartments, meanwhile, are suffering tech issues where placing meters and in-home displays in sufficient proximity to each other is difficult.  Pilots are underway to solve the problem.

Meanwhile, thousands of homes in remote areas of the UK such as the Highlands and Islands of Scotland have lower mobile coverage, and thus, lower smart meter numbers. This is certainly set to impact Australians living in mobile black spots, too.

Here in Australia, challenges installing smart meters for renters, those in older dwellings and apartments, or those with less money, is generating momentum in Australia’s emerging Great Energy Divide.

For instance, almost 20% of smart meter installations are postponed or cancelled when engineers encounter issues like asbestos or damaged meter boards. Australian energy customers are currently responsible for any remediation work required for a smart meter to be installed. Consequently, customers unwilling or unable to pay for remediation requirements are falling behind.  Renters are also disadvantaged, unsure if they can request a smart meter. The AEMC is said to be working on financial assistance packages to remove this cost to consumers. In the UK, meanwhile, regulators are working to improve communications to landlords explaining perks to encourage greater uptake of smart meters.

5. Skills Shortages Impacting the SM Rollout

Another hurdle to reaching smart meter rollout targets in Australia and the UK is a shortage of skills required for installations, slowing progress, and adding to costs.

UK suppliers report a steady decline in the availability of installers – approximately 14% since March 2020. Similarly, a shortage of technicians and trades has impacted Australia’s economy for years now. The latest Jobs and Skills Australia report states less than half of jobs advertised for Technicians and Trades is filled.

Competition amongst Australia’s energy retailers for electricians is already high, and only set to become higher under an accelerated smart meter plan. Costs incurred by the retailer for in-demand skills are ultimately passed on as smart meter costs to Australian energy consumers.

6. Tech Hurdles Slowing Smart Meter Rollouts

In June, research finds more than one in ten, or 4.31 million of the UK’s smart meters aren’t working for one of three reasons:

  1. Poor Installation Practices: Over one million smart meters aren’t working because they haven’t been commissioned properly during installation. In some instances – like a new building – this is intentional, but the majority are faulty installations. A revisit is required to fix this issue at unknown cost.
  2. Supplier & Smart Meter Records & Processes: almost one million smart meters aren’t working where owners have switched suppliers and the process hasn’t been executed as planned (ie. a new customer isn’t recognised as a smart meter owner). These issues can be resolved, but add to growing ‘un-factored’ time and cost factors.
  3. Outdated Tech: Over 1.4 million smart meters have lost communications. This includes first-generation meters (SMETS1 devices) which require re-connection to continue working once a customer switches suppliers. The department says up to half a million of these consumers may not be able to reconnect, thus requiring replacement smart meters.

Soon, a further seven million UK smart meters won’t work once 2G and 3G communications are switched off. Meanwhile in Australia, a yet unknown number of smart meters are set to be impacted by our own local 3G switch-off.

Of course, the slower any technology rollout, not only do consumers miss on the proposed benefits, but the higher the chance tech redundancy becomes an issue before implementation is complete.

In combination with rewarding new installation numbers, rather than re-installations, fixes, or the quality of installation, the cost of smart meter rollouts continues to mushroom. Costs which are ultimately, paid by consumers who, aren’t yet realising smart meter benefits as planned.

Further, it’s evident that more consideration needs to be paid to life after these accelerated smart meter rollouts, too. Neither UK nor Australian energy regulators have forecast ‘business as usual’ costs, once smart meter implementations are complete. For instance, maintenance of smart meters is much more complex than their analogue equivalent; software patches and cybersecurity fixes, and cost of replacement must be factored in.

Conclusion

If we’re going back to the drawing board in an attempt to fix Australia’s smart meter rollout, the AEMC review should go beyond the speed at which SM’s can be implemented, and rather consider how alternative means to reach 100% digitisation of the NEM can save time, money and satisfy National Energy Obligations (NEO) without further embarrassment, inequality and delays.